← CEAtlas · Guides

Route finder: how it works and how to use it

The route finder draws the least-cost route for a new transmission line — from a site to the grid, or between two points — and prices it with low, central and high estimates. It weighs terrain, land cover, protected and sensitive areas, ground conditions, land values, water, and the roads, railways and lines a route has to cross. It is a screening tool: it shows where a line can run and roughly what it will cost, before you commission a routing study.

Part 1 · Method

At a glance

Two modesSite to grid, sized by your project; or a line between two points you choose, with stops along the way if you need them.
Three line typesAC overhead, HVDC overhead and HVDC cable. Overhead lines can cross sea and lakes by submarine cable.
Up to 10 routesThe best route and its alternatives, at most three on a long line or one crossing water, a cost corridor, and every cost item with a range.
WorldwideRouted and priced at 100 m in the contiguous United States, Great Britain and Europe, however long the line, with water at 1 km; 2 km on other continents; 5 km for a line between continents or too long for the 2 km grids.
Copenhagen → Malmö, 400 kV ACAbout 41 km, about €68m. It crosses the Øresund by about 14 km of AC cable, with a landfall on each shore, and steers round the protected areas at sea.
Toronto → Montreal, 230 kV AC566 km, about $498m, along the St Lawrence corridor and round the parks it meets.
Bacton → IJmuiden, 2 GW HVDC cable234 km straight across the North Sea if marine protected areas may be crossed; 765 km round them if not.

Examples computed in November 2026 with the default settings; central estimates.

What a kilometre costs

Each cell's price per kilometre is built from the items below. Every item has a low, central and high value, and a route's range is the sum of its items.

ItemWhat it isSource
LineThe cost of the line itself for its voltage and region, times the local price level (none on the 1 km and 100 m grids of the contiguous United States, where the region's price table stands) and, since November 2026, on the 1 km and 100 m grids of the contiguous United States, Great Britain and Europe, the local labour factor: 1 + 0.35 × (the cell's construction crew-wage index ÷ the index of the line's own price basis − 1) — in the United States the BLS OEWS May 2025 index relative to the mean of the line's cost region (whose price table already carries the region's labour), in Great Britain and Europe the local authority / NUTS 2 index relative to the country mean (the country level already carries the country's labour). Wage-only: productivity is not adjusted. A line searched on the 2 km or 5 km grids, wherever it runs, takes ACER's European figures at the price level alone.Contiguous United States: NREL reVX transmission costs. Great Britain and Europe: ACER Unit Investment Cost Indicators 2026. Elsewhere, and on the 2 km and 5 km grids: ACER's European figures scaled by the country's construction price level (World Bank ICP 2021).
Terrain and land coverA multiplier for slope and for land cover. Slope: ×1.1 to ×1.5 where the mean slope is 3° or more, and ×1.2 to ×2 on ground steeper than 10° (by region; the western US is highest) — rising with steepness to twice that at 30°, so a route keeps off the steepest ground when it can. Land cover: wetland, forest and built-up ground cost more (in the central US wetland ×1.8, forest and urban ×1.2, suburban ×1.08, cropland ×1.03; forest up to ×3 in the western US), blended by each cell's mix of cover.NREL reVX multipliers; the rise above 10° is our own allowance. Slope from Copernicus GLO-90 or ETOPO 2022. Land cover from NLCD (contiguous US), Impact Observatory (Europe) and Copernicus LC100 (elsewhere).
Sensitive areasCrossing a sensitive designation costs 2.5 times the normal line cost there (1.25 times for a buried cable) — an allowance for consenting, mitigation and partial undergrounding.National protected-area datasets (see sources).
Ground conditionsExtra foundation and civil cost where the ground is difficult: peat, soft ground, shallow rock, karst, landslide-prone slopes, mining areas, landfill and contaminated land.National geological and land-condition data (contiguous US, GB, Europe).
EasementPayment for the right of way: the land's value × the corridor width (23–61 m, by voltage) × a share of the value (a quarter to all of it; half as the central case).Modelled land values from official farmland and land-price data (contiguous US, GB, Europe).
Access tracksWhere a line runs more than 1 km from any road, a construction track along it: about $119,000 per km for a gravel track ($233,000 for a heavier one at the high end), times the slope multiplier, the local price level and the local labour factor (as the line; in the contiguous United States the labour factor alone, with no price level). The contiguous United States, Great Britain and Europe.Texas DOT road-base prices with typical track volumes (US $ of 2026). Roads from US Census TIGER, Ordnance Survey Open Roads and OpenStreetMap.
ConnectionSite to grid only: a bay at the substation, or a new substation on a line, at the local price level and the local labour factor (as the line; in the contiguous United States the labour factor alone, with no price level).Published substation unit costs.
Substations at stopsAC lines with substation stops: a new substation on the line at each, at the local price level and labour factor (the same factor as the line, labour share 0.35; on the 1 km and 100 m grids of the contiguous United States the labour factor alone, with no price level; on a section searched on the 2 km or 5 km grids the price level alone).Published substation unit costs.
Converter stationsHVDC only: one at each end and one at each converter stop, priced per MW of the link. Each station is priced where it stands, whichever grid the route was searched on: a line that leaves the 1 km grids, runs out of time on them or finds no way on them is searched on the 2 km or 5 km grid, and the line itself is priced there, but a station inside the contiguous United States, Great Britain or Europe keeps that place's price. A station's equipment, 68 % of the price, stays at one price; its local part (civil works and buildings, erection and commissioning, engineering), about a third (32 %), takes the local level at that station's own place, so the two ends can differ: the per-MW price × (0.68 + 0.32 × the local level). In Great Britain and Europe the local level is the country's price level × the local labour factor. In the contiguous United States it is the labour factor alone, each place against its cost region's average, with no price level; California is its own cost region, so a station there pays the per-MW price unchanged. Anywhere else, on the 2 km and 5 km grids, it is the price level alone, on the European per-MW price in US dollars. A station on water has no local factor.ACER 2026 (Europe and elsewhere); MISO 2025 via NREL ReEDS (contiguous US). The local part: Rudervall, Charpentier and Sharma, Energy Week 2000 (ABB and the World Bank), a year 2000 figure for the older converter type, transferred to today's.
Water crossings and landfallsSubmarine cable where a line crosses sea or a lake, and a substation bay at each landfall. The bay is at the local price level and the local labour factor (as the line; on the 1 km and 100 m grids of the contiguous United States the labour factor alone, with no price level; on the 2 km or 5 km grids the price level alone); the cable carries neither.ACER 2026 submarine cable costs; for an AC cable in the contiguous United States, four times ACER's price (see Line types and water).
Underground sectionsHVDC overhead lines only: buried HVDC cable where the line goes underground, with the terrain multipliers, ground conditions and half an overhead line's easement; 1.25 times in sensitive and protected areas.ACER 2026 DC cable costs (twice the cable on land in the contiguous United States: two cables, for redundancy).
Overhead–cable transitionsA substation bay wherever an overhead line meets its underground cable.Published substation unit costs.
Significant crossingsAn allowance each time the route crosses a motorway or trunk road, an active railway, a navigable waterway or another line of 100 kV or more: the cost of 0.8 km of the line (0.7 to 0.9 km for the range). A crossing counts where the route passes over the feature to its other side — not at the route's own ends, and not where it only runs alongside. Crossings very close together can count as one; cable sections at sea pay none.IET / Parsons Brinckerhoff, Electricity Transmission Costing Study (2012).

Outside the contiguous United States, Great Britain and Europe, the easement and ground-condition items and the local labour factor are not included, because there is no consistent land-value, ground or local wage data. The result says so. The access tracks and the rise in the slope multiplier above 10° are not included there either, because those grids hold no distance to the nearest road and keep the plain slope classes.

The grid connection on the Site Development Cost map uses the same line costs, terrain and land-cover multipliers, sensitive-area costs and ground conditions and, since November 2026, in the contiguous United States, Great Britain and Europe, the steepness above 10° and the access tracks. The main differences: it has no easement, because that map prices the site's land separately; it has no allowance for significant crossings; it searches on the 1 km grid, with no 100 m search; and it prices the whole route at the site's local price level and labour factor, not each cell's. On protected land, military land and airports, which this route finder does not go through by default, on open water, which it crosses by cable by default, and on ground too steep to build on, which it does not cross, that map charges 10 times the line's cost per km instead: a heavy penalty rather than a block, so a connection goes round such ground when that is cheaper. A site on or behind too-steep ground keeps a figure, and that figure does not say the ground can be built on; on that map's click, and on the Grid Connection by Size and Site Value clicks, a site on such ground is told so. A site inside a no-go area, or with no grid of the connection voltage reachable over land, has no figure. A click at the edge of such a cell can still show a figure, read from the cells around it, and the card says so.

Obstacles and exclusions

Everything on the map falls into one of three treatments. No-go areas are removed from the search: on the 1 km and 100 m searches a route never enters them and goes round, however far (the 2 km and 5 km grids can cross a strip narrower than a cell and, where that is the only way through, an airport, and the answer then says so: see Coverage and resolution). Priced areas can be crossed but cost more, so a route goes round them when that is cheaper and through them when it is not. Weighted conditions raise the price of a kilometre without ever blocking it.

ObstacleTreatmentDetail
Strictly protected land: national parks, wilderness and nature reserves (IUCN Ia, Ib and II; US GAP 1 and 2; UK National Nature Reserves)No-goEach can be switched off in the panel so a route may cross it; the result then says how many km it crosses.
Military landNo-goWhere mapped: US federal military land, and OpenStreetMap outside the US and Europe. Can be switched off.
AirportsNo-goCan be switched off. From OpenStreetMap: its airport points, and the airports it maps as areas, O'Hare, Dallas/Fort Worth, Denver, Orlando, Heathrow, Frankfurt, Madrid and Paris Charles de Gaulle among them, whose outlines on land are no-go too. An airfield with no outline here, one OpenStreetMap maps as a point alone or whose outline fits inside its point's square, is no-go only as that square: with an IATA code about 2.1 km across on the 100 m map and 3 to 4 km on the 1 km map, any other about 700 m on the 100 m map and, on the 1 km map, every 1 km cell that square touches, usually two or four. Of the outlines in Great Britain, Europe and the United States, those tagged or named closed, abandoned, disused or historic are left out, apart from three working airfields so tagged (College Park near Washington, Stanton and Southern California Logistics), and so are those with no name under 0.05 km². That is the outlines alone: the airport points do not test those tags, so most closed fields keep the square round their point until that file is refreshed. The regional extracts the 2 km and 5 km grids read elsewhere, in Ukraine, Belarus, Moldova and Georgia too, do not test them either. Lines outside the 1 km and 100 m maps, and a long line whose 100 m search runs out of time, run on the coarser 2 km and 5 km grids; on the 5 km grid, where a cell is 25 km², the United States and Europe read only an airport with an IATA code from these points and outlines, and OpenStreetMap's regional extracts keep their rule; elsewhere that grid reads those extracts alone, which miss many small coded airstrips, so a long line there can cross one; an airport on an island too small to hold a land cell at that size, or beyond 78° N or 60° S where that grid stops, has no cell there.
Lakes and open waterNo-go for a line on landCrossable by cable when the water crossing is switched on (see line types).
Marine protected areasNo-go for cablesCan be switched off; a cable may then cross them at 1.25 times its cost.
Sensitive designations: Natura 2000, SSSI and ASSI, SAC, SPA, Ramsar sites, national parks and landscapes, and other national designationsPriced2.5 times the line cost per km inside (1.25 times for a buried cable). The pricing can be switched off.
Steep and mountainous groundWeightedSlope multipliers, rising with steepness.
Ground too steep to build on: steeper than 30° for a buried cable, 35° for an overhead lineNo-goAt 100 m, every cell that steep; on the 1 km grid, a cell when more than half of it is. The contiguous United States, Great Britain and Europe.
Ground far from any roadWeightedAn access track per km where the line is more than 1 km from a road (see costs), so a route keeps to accessible ground when that is cheaper.
Forest, wetland, cropland and urban areasWeightedLand-cover multipliers, wetland the highest at ×1.8.
Difficult groundWeightedGround-condition costs per km (contiguous US, GB, Europe).
Valuable landWeightedEasement cost per km (contiguous US, GB, Europe).
Road, railway, waterway and line crossingsWeightedEach crossing of a motorway or trunk road, an active railway, a navigable waterway or another line of 100 kV or more adds an allowance (see costs). The 100 m search weighs crossings too, so a route avoids needless ones. Narrow rivers are spanned by an overhead line; wide estuaries and lakes are treated as water.

Narrow necks of land. On the 1 km first pass a cell that a no-go area touches is no-go whole: protected land, military land, an airport's outline or the square round its point. A cell too steep at 1 km is closed the same way. That can close a neck of land that is open on the ground. When the first pass finds no way out for a point, it checks at 100 m which of those cells the point's ground really reaches, and only the first pass may step through them. The final 100 m route goes round every no-go area by its true outline, or the line is refused. Those cells never count in a route's price, its corridor or the search picture. An answer found that way carries no note: the route goes round the outlines.

A click on an airport. When a site or an end of a line stands on an airport and the search cannot leave it, the answer says that the point is on an airport, names it where it can, and says what to do: move the point off the airport, or untick Airports. The same goes for protected land and military land. A point on an airport with clear ground beside it can still answer; if no route is found from it, the refusal keeps its own advice, on water crossings too, and adds that the point is on an airport. The other refusals keep their own words: a point on clear ground is told that no connection or no route was found.

How strict the avoidance is. On the 1 km first pass, a cell that touches protected land counts as no-go, so a gap narrower than about 1 km between two protected areas may not be found if the line has another way; the 100 m search uses such a gap when it lies near the route. On the 2 km and 5 km grids, a cell is no-go when its centre is inside, so a protected strip narrower than the cell may be crossed. The 100 m search then follows the actual boundaries.

Line types and water

Line typePer kmWater
AC overhead line
by voltage
The published line cost for the voltage and region.Crosses sea and lakes by AC submarine cable (ACER median €2.30m per km; four times that, about $11m per km, in the contiguous United States), each crossing at most 50 km. Longer stretches of water need HVDC.
HVDC overhead line
±500 kV bipole, about 3,000 MW
0.827 times the region's highest-voltage AC line, plus two converter stations. Can go underground in sections (see below).Crosses sea and lakes by HVDC cable.
HVDC cable
buried on land, laid on the sea bed
ACER DC cable €1.01m / €1.38m / €1.56m per km (low / central / high) for a link of up to 1,400 MW; a larger link pays in proportion (3,000 MW about 2.1 times). In the contiguous United States the cable costs 2.6 times ACER's figure, about $4.3m per km at sea, and a buried cable on land costs twice that per km — two cables, for redundancy. Plus two converter stations.Cable throughout. On land it carries the terrain multipliers, ground conditions and half an overhead line's easement.

Water can be crossed only where it is no deeper than the limit you choose — from 50 m to 1,000 m, with 200 m (roughly the continental shelf) as the default. Depths come from NOAA's ETOPO 2022 model; a lake's depth is measured from its own surface. Each landfall, where an overhead line meets its cable, adds the cost of a substation bay at the local price level and the local labour factor (on the 1 km and 100 m grids of the contiguous United States the labour factor alone, with no price level; on the 2 km or 5 km grids the price level alone), and the search weighs the cable and the landfalls against the way round on land. It makes that choice at 1 km, and the final price is worked out at 100 m, so the two can differ: a line with water allowed can come out dearer than the same line with it not allowed. To compare, run the line again with the box unticked.

An AC crossing is kept within 50 km because an AC cable's charging current limits how far it can run. If the cheapest route would need a longer AC crossing, the finder looks for another way round; if there is none, it says so and suggests HVDC. Each alternative route is held to the same limit.

Why an AC cable costs more in the contiguous United States. There the finder prices an AC submarine cable at four times ACER's European figure: about $11m per km, with a range of about $7m to $13m. ACER publishes one price across voltages, and its sample looks mostly lower-voltage. We found no public per-km price for a 345 kV AC submarine cable in the United States, so this is an estimate, and what it rests on is not like for like. Two US 138 kV projects, both replacements: $105m for two circuits across about 4 miles at the Straits of Mackinac in 2021, taking out the old cables too, and $140m for about 11 miles under Long Island Sound in 2008. Against those, a contract of about €68m in 2021 for the cable alone, 37 km at 132 kV, from Elba to the Italian mainland. New England's planners put an underground line at more than four times a new overhead line, the same gap ACER's figures show in Europe between its cable and its overhead line. The factor prices one circuit: a crossing that must carry as much as a large overhead line would need more, and at the lowest voltages it may read high. Great Britain, Europe and the 2 km and 5 km grids keep ACER's price, and the HVDC cable has its own price.

Why an HVDC cable costs more in the contiguous United States. There the finder prices an HVDC cable at 2.6 times ACER's European figure: about $4.3m per km at sea for a link of up to 1,400 MW, with a range of about $3.2m to $4.9m, and twice that on land, where it is two cables. New England's grid operator, in its 2050 Transmission Study, puts an HVDC cable at $10.5M per mile in 2023 dollars, a figure from the National Renewable Energy Laboratory with a 50 % contingency added; without the contingency that is about $4.3m per km. The finder adds no contingency to any other line, so it leaves this one out too, and it does not bring the 2023 dollars forward, so it may read a little low. The study does not say how large a link its cable carries; the offshore links it looks at are 1,200 MW. This is an estimate. An HVDC overhead line's water crossings and underground sections use the same cable price, and so does an HVDC link sent to Scenario Studio. Great Britain, Europe and the 2 km and 5 km grids keep ACER's price.

HVDC overhead lines: overhead, underground, or both

For an HVDC overhead line between two points, the route finder shows the options side by side, each labelled and sorted by cost:

Underground sections may pass under airports, and under protected land priced as a cable in a sensitive area (1.25 times); they never cross strict wilderness or military land. Each change between overhead line and cable adds a substation bay. If no overhead route exists at all — for example, from a town inside a national park — the line goes underground where it must, and the result says so. On the 1 km grid a route with underground sections stays at 1 km for now, with no 100 m pass; on the 2 km and 5 km grids it stays at that grid's resolution. A very long line shows the options beside the overhead route only if the time allowed for the search lets them finish, and the result says when it does not.

Coverage and resolution

AreaGridCosts
United States (lower 48), Great Britain, Northern Ireland and Europe100 m routes on land, however long the line
(coarse and 1 km first passes)
Regional cost data, with ground conditions and easements; answers in $, £ or €. Water stays at 1 km.
Everywhere else on land: the Americas, Africa, the Middle East, Asia, Russia, Australia and New Zealand, Alaska and Hawaii2 kmACER costs × the country's construction price level; answers in US $.
Cross-continent lines, and lines too long for the 2 km grids (for example, the UK to North Africa)5 kmThe line as above; each converter station is priced where it stands.

There is no fixed length limit. With both ends in the contiguous United States, or both in Great Britain, Northern Ireland and Europe, a line's land is routed at 100 m however long it is: a coarse search finds the way, a 1 km search the corridor, and the 100 m search runs along it. A long line, or one that crosses water, can take a minute or more, and shows at most three routes; a long line's corridor is shaded on 4 km blocks. Any other line takes the finest grid that holds both ends: 2 km, or the 5 km world grid for a line between continents or one too long for the 2 km grids. The result always states the resolution it used and, when it moved to a coarser grid, why. A line crossing the Pacific's date line cannot be routed.

What falls back, and says so. If the 100 m search runs out of the time allowed, a long line is answered from the 2 km or 5 km grid, and a shorter one crossing water stays at 1 km, each with a note on its result and on its print. The 2 km and 5 km grids' price table reads lower than the 100 m table on long lines, so a price from that fallback is not comparable with a 100 m answer, and trying again may give the 100 m answer. Such a price is marked provisional wherever it can be read: the saved route, the CSV, the GeoJSON, the KML and what goes to Scenario Studio. If no 100 m way exists on one part of a line, that part is drawn and priced at 1 km and not confirmed at 100 m, and a note says where and why. A part that would run through a cell the 1 km map closes, other than the cell an end of the line stands in, never stays at 1 km: the line keeps the 1 km answer its first search gave, or is refused if it had none. A search that covered the whole area round a line and found no way stands: no coarser grid overturns it, and where the AC crossing limit was the reason the answer says to try an HVDC line type. A line too long for that search, or whose search area could not widen as far as it asks, goes on to the 2 km or 5 km grid, with a note, when the ground at an end is too large to check at 100 m, or when the line may cross water by AC cable, and is refused if that grid finds no way either. Any other line with an end shut in on smaller ground is refused at once.

Why long lines cost more than they used to. A kilometre now costs the same however long the line. Long lines in the contiguous United States and Europe used to run on the 2 km and 5 km grids, on the international default price; they now run at 100 m on the same regional table as every shorter line. Their published prices rise: a 345 kV line from Dallas to New York, which the 2 km grid priced at its nearest class, 400 kV, goes from about $4.0bn to about $7.3bn, and it is also a shorter route. On other continents the international default stays, as there is no regional table.

A route answered from the 2 km or 5 km grid carries a note on its result and on its print: the line was searched at that resolution, so it can cross no-go areas narrower than a grid cell, which the 1 km and 100 m searches go round; and its line price uses the European cost table times a national level, which can differ widely from the finer grids' price. A 1 km or 100 m answer carries no such note.

On the 2 km and 5 km grids a line can cross an airport where that is the only way through. Those grids have no 100 m search. When the first search finds no way and Airports is ticked, it searches again with airport cells very expensive, so the line crosses as few as it can, and the answer says so on its result and on its print, naming the airport where it can, and saying the search was coarse. The result's Crosses row gives the distance. If that search finds no way either, the first refusal stands. With Airports unticked, or when the first search finds a way, none of this happens.

Accuracy and limits

The route finder is for screening. Use it to compare options, see where a line can and cannot go, and get an order-of-magnitude cost early, before a routing or feasibility study.

Part 2 · User guide

Finding a route

The route finder is in the sidebar under Markets, Economics & Analysis › Studies › Route finder, on desktop, for Desk subscriptions and above.

  1. Choose a mode. Site → grid to connect a project, or Line between two points for a link.
  2. Choose the line type. AC overhead (the default), HVDC overhead or HVDC cable. For HVDC between two points, set the link rating in MW (2,000 by default). For an HVDC overhead line, Show a route with underground sections is ticked by default; untick it to see the overhead route only (it still goes underground if there is no other way).
  3. Set how many routes you want, from 1 to 10.
  4. Water. For overhead lines, Cross sea and lakes by cable is ticked by default; untick it to make the line go round. Set the deepest water a cable may cross.
  5. Pick your points. For a site, click Pick site, click the map and enter the project size in MW. For a line, pick A and B and choose the voltage.
  6. Add stops (optional). For a line, click Add stop and click the map, once for each stop (up to eight); the line passes through them in order from A to B. For each stop choose what it is — a pass-through point, or a station (a substation on an AC line, a converter station on an HVDC line). Use ↑ to move a stop earlier and × to remove it.
  7. Check the no-go and sensitive options. Every no-go layer is avoided by default. Untick any you want a route allowed to cross, or switch off sensitive-area pricing.
  8. Click Find routes. The search plays out on the map — in the contiguous United States, Great Britain and Europe in two stages, the 1 km search and then the 100 m search over the corridor — then the routes draw themselves and the result opens.

Reading the results

On the map

The result

Every route lists its length (and the straight-line distance), its total with a low–high range, and each cost item; with stops, each section's length and cost too. Click a route for what it goes over — named designations with their km, ground conditions, km by terrain difficulty, and the motorways, railways, waterways and power lines it crosses — and what it goes round: the named no-go areas within 10 km and how far away it passes.

Taking it further

Data sources

InputSourceLicence
Line, substation, cable and converter costsNREL reVX and ReEDS-2.0; ACER Unit Investment Cost Indicators 2026; MISO Transmission Cost Estimation Guide 2025 (via ReEDS); for the US AC cable, ISO New England 2050 Transmission Study (2024), American Transmission Co. (Straits of Mackinac, 2021), Engineering News-Record (Long Island Sound, 2008), Prysmian (Elba to Piombino, 2021), NYISO and New York DPS (Propel NY)BSD-3 (NREL); cited figures (ACER, MISO, the rest)
Crossing allowanceIET / Parsons Brinckerhoff, Electricity Transmission Costing Study (2012)Cited figures
Converter station cost structure (its local part)Rudervall, Charpentier and Sharma, High Voltage Direct Current (HVDC) Transmission Systems Technology Review Paper, Energy Week 2000 (ABB and the World Bank)Cited figures
Country price levelsWorld Bank International Comparison Program 2021CC BY 4.0
Elevation, slope and water depthCopernicus DEM GLO-90; NOAA ETOPO 2022Copernicus licence; US public domain
Land coverUSGS NLCD; Impact Observatory / Esri 10 m; Copernicus Global Land Service LC100 2019Public domain; CC BY 4.0
Protected and sensitive areasUSGS PAD-US 4.1; EEA Natura 2000 and Nationally Designated Areas; Natural England, NatureScot, Natural Resources Wales, DAERA; NOAA Marine Protected Areas Inventory; OpenStreetMap elsewherePublic domain; CC BY 4.0; Open Government Licence v3.0; CC0; ODbL
Roads, railways and waterways (crossings)US DOT NTAD and Census TIGER, FRA / BTS rail, USACE / BTS waterways (US); OS Open Roads (GB); OpenStreetMap (Europe and elsewhere)Public domain; Open Government Licence v3.0; ODbL
Substations and linesOpenStreetMap, PyPSA-Eur and HIFLD, as on CEAtlas's Transmission layersODbL; CC BY 4.0
CountriesNatural EarthPublic domain

Full attributions are on the licences page.